RFIs and decisions
Construction RFI Workflow from Question to Site Closeout
Write a decision-ready request for information and turn the response into controlled instructions for the site, procurement and programme teams.
A request for information (RFI) should make it easy for the reviewer to give a usable answer. “Please clarify the ceiling” gives the reviewer no location, no conflicting references and no deadline tied to the work. A well-written RFI describes a decision the project needs and the activity that depends on it. Closeout is the point at which the answer reaches those who need to act, with a traceable record of what changed.
Ask one question with enough context
Use a title that includes the package or location. State what the team sees in the current documents, including the revision of each conflicting reference. Add a marked-up view if it helps. Ask for a specific clarification and give a response date based on the last responsible decision date. If an option is offered for review, state its assumptions and constraints. Keep technical direction and contractual authority with the responsible parties under the project procedure.
Worked example — two drawings for one bulkhead
The fit-out team finds two soffit levels in the issued architectural and services drawings. Record the affected grid lines, both drawing revisions and the date when fabrication needs the dimension. Ask the design lead to confirm the governing level and issue the coordinated detail. When the response arrives, check it against the question. Link the updated sheet, identify whether a commercial or programme review is needed and brief the supervisor before the affected fabrication is released.
What the November 2026 software update changes
Autodesk describes placing an RFI against a location on a sheet and assigning the action to a role or company in Forma Build. Those functions help teams locate and route a question. Define who monitors a shared queue and who is responsible for the next decision. If the drawing changes later, retain the original revision reference so a pin can still be interpreted in context.
Check before closing
- Does the response answer the specific question and identify a governing document?
- Has the answer been distributed to the supervisor, planner and commercial team when relevant?
- Are follow-on actions, revision changes and any contractual notices recorded through the agreed channels?
- Can another reviewer follow the original question to the instruction and its acknowledgement?
Video walkthrough
Follow the routing and response steps. Then write a separate action for the person who needs to distribute the final answer to the site.