Inspection and Test Plans That Protect Construction Hold Points
Build an inspection and test plan around release decisions, collecting usable field evidence before work is covered.
An inspection and test plan (ITP) works best when the next crew knows when it can start. A form filled out after concealment can be hard to verify. Place inspections at the points where defects are visible and corrections are still practical. Define the hold and witness arrangements in the project's approved plan, including notice periods, the authorised person and the permitted response to a missed inspection.
Start with the decision and work back to the evidence
Write each inspection around a specific activity and location. Reference the specification or inspection criterion and show what evidence demonstrates the result. This might be a reading, a certificate, an annotated photograph or a witness record. A timestamp alone rarely proves which location was checked. Link the record to the work package or lot so that it remains findable even if the folder structure changes.
Worked example — closing a services riser
The team is preparing to close a riser. The supervisor uses the approved checklist to confirm which inspections and sign-offs are required before enclosure. A photograph includes a location marker and is linked to the inspection reference. An unresolved item is entered in the defect register with an owner and a reinspection date. The follow-on crew receives the release for the named location only once the authorised person records the decision. A nearby riser with incomplete evidence stays outside that release.
Translate the decision into a field form
Autodesk's November 2026 notes describe configurable plan types for Workplan, and place-on-sheet forms as a beta. Start a pilot with a plain location reference and a named release owner that work even without pins. Test access and sync in a representative offline area, and keep a documented backup process for loss of connectivity. Verify the applicable technical acceptance criteria with the responsible specialists.
Before concealment
- Confirm the current ITP and supporting design documents.
- Record location, result and exceptions using evidence another person can verify.
- Agree corrective work and repeat checks where required.
- Make the release decision visible to the follow-on team and retain its reference.
Video walkthrough
Observe how a form is created and completed. Add a requirement to capture the exact location and accepted drawing revision in your practice record, then try retrieving the evidence from a phone.