Wood Framing Project Management & BIM

Planning & controls

Construction Planning & Project Controls

Developed construction programmes and project-control records using MS Project and Excel. Connected activity sequencing, quantities and material requirements with progress review, site coordination and quality-record tracking.

Open interactive project gallery →
Explore selected evidence ↓
Construction Planning & Project Controls — Programme Gantt view

Project scope & involvement

Focus
Planning, controls & quality records
Tools
MS Project & Excel

Construction management case study

My role, decisions & delivery record

My role & scope

Developed construction programmes and project-control records using MS Project and Excel. Connected activity sequencing, quantities and material requirements with progress review, site coordination and quality-record tracking.

The challenge

Site activities, dependencies, quantities and material requirements needed a consistent basis for planning and progress review.

My actions & decisions

I developed construction programmes and project-control records using MS Project and Excel, connecting activity sequencing with quantity, material and quality tracking.

Result & delivery record

Gantt charts and Excel records form the planning and control output presented in the portfolio.

Selected evidence

Delivery sequence & selected records

Programme and quantity excerpts from my supplied portfolio, followed by selected management-control examples. Each example retains its own project context.

Source drawings and record excerpts are identified separately from portfolio summaries and presentation visuals. Presentation visuals explain the project setting, including reference-based or presentation views; they are not original site or approval records.

Programme sequencing and dependenciesProgramme excerpt · MS ProjectConstruction Planning & Project Controls — Programme sequencing and dependencies (Programme excerpt · MS Project)

Activities, WBS levels, dates and linked Gantt bars show the programme structure used for sequencing review.

My role: I use programme logic and activity dependencies alongside quantities to coordinate procurement, technical information and site priorities.

Portfolio p. 03 · Programme Planning & Quantity Control

Open image at full size ↗
Measured quantities and material requirementsQuantity-record excerpt · ExcelConstruction Planning & Project Controls — Measured quantities and material requirements (Quantity-record excerpt · Excel)

The excerpt groups measured work and material quantities, including excavation, reinforcement and concrete.

My role: I review measured quantities against material requirements and programme priorities to support procurement coordination.

Portfolio p. 03 · Quantity records

Open image at full size ↗
Finishes and follow-on work quantitiesQuantity-record excerpt · ExcelConstruction Planning & Project Controls — Finishes and follow-on work quantities (Quantity-record excerpt · Excel)

The complementary excerpt covers floor, roof, wall, insulation and finishing quantities.

My role: I connect quantities and timing so follow-on activities can be reviewed together with material demand.

Portfolio p. 03 · Quantity records

Open image at full size ↗
Technical query through site verificationPortfolio case summary · selected office coordination

MEP-042 → CM-12 / RFI-028 → Docs P04 → SC-031. The portfolio describes a services reroute followed through the issued revision and site check, with the structural member retained.

My role: I coordinated the MEP and structural designers’ response, reviewed access, sequence and procurement implications, and followed the approved revision through site verification.

Portfolio p. 06 · Selected office-project record; project name not specified

Change pricing and programme reviewPortfolio summary · selected commercial package

V-017: access panels and duct offsets, USD 24,000, two working days within available float. V-021: tenant counter layout, USD 18,500, no critical-path impact.

My role: I linked technical queries, pricing and programme review before approved changes proceeded to installation. Approval remained with authorised decision-makers.

Portfolio p. 07 · Selected commercial change decisions

Defect closure and handover informationPortfolio summary · quality and close-out

The selected quality record reports 280 of 286 items closed at handover (97.9%), with the remaining six closed within 14 days. The handover information families include as-built drawings, test records, warranties and O&M information.

My role: My documented delivery work connects workmanship checks, assigned actions and close-out follow-up with the information needed for handover.

Portfolio pp. 08–09 · Quality, handover and coordinated release

Related project experience

Explore construction project management experience and BIM and project delivery guides.

Further reading on the coordination topics relevant to this portfolio record. These guides do not imply that every method or software tool was used on this project.

Construction and architecture visual record

Images accompanying Construction Planning & Project Controls: Wood Framing Project Management & BIM. The project description identifies Saeed Azarshab’s construction project management involvement; photographs, technical drawings and illustrations are identified individually in the captions.

تصاویر پروژهٔ Construction Planning & Project Controls در مجموعهٔ فعالیت‌های سعید آذرشب؛ سوابق تصویری ساخت‌وساز، اجرا و معماری. نقش مدیریت پروژه و نوع هر تصویر، نقشه یا تصویر توضیحی در متن و زیرنویس همان پروژه مشخص شده است.

Professional opportunities

Discuss a construction management role

Explore my construction-delivery case studies and professional background, download my portfolio or get in touch.