Construction management insights · 2026-09-26

Recovery That Can Be Delivered

By Mohammadsaeed Azarshab · Originally shared on LinkedIn

An earlier date is not a recovery plan.

When I look at an activity that has been moved forward, I want to know what changed to make that earlier start possible.

Has the preceding work been released? Is the required information approved? Can the trades share the area without creating a new constraint? Are the necessary people and materials available?

Those questions shaped the Programme Controls view in Mehraz Negar, the construction-management platform I designed and developed.

The view brings work packages, dependencies, critical-path information, float, milestones and baseline-versus-current programme information into one review context.

The management task is to use that context well.

Consider a proposal to overlap two activities. I would want the planner and delivery team to explain which work can genuinely proceed in parallel, what access is required and which inspections or technical approvals must remain in sequence.

I would also want the commercial consequences and any transfer of risk made visible. Saving time in one area is not enough if the proposal creates an unmanageable problem for another trade.

The agreed response then needs an owner, the appropriate approvals and a way to check whether the revised forecast still holds as work progresses. I would keep the approved baseline visible rather than overwrite the original commitment.

The software supports that conversation. It does not replace the planner’s judgement, specialist review or the authority required to approve a change.

For me, programme control means being able to explain why a date is achievable—and what the team must do to make it so.

What evidence would you ask for before accepting a recovery proposal?

Accompanying visuals

MEHRAZ NEGAR / PROJECT CONTROLS 02 MOHAMMADSAEED AZARSHAB | CONSTRUCTION PROJECT MANAGER 1 / 3 Interface visualisation. Displayed values are illustrative, not verified project results. An earlier date is not a recovery plan. Challenge the constraint, not just the bar on the programme. What changed on site to make that earlier start possible?
Visual 1 of 3
MEHRAZ NEGAR / PROJECT CONTROLS 02 MOHAMMADSAEED AZARSHAB | CONSTRUCTION PROJECT MANAGER 2 / 3 Interface visualisation. Displayed values are illustrative, not verified project results. The management questions behind the interface. READ THE LOGIC, NOT JUST THE DATES Review scope, dependencies, float and the milestone affected. Test the recovery proposal Check feasibility, consequences, responsibility and approval. SELECTED DETAILS FROM THE SUPPLIED INTERFACE VISUALS
Visual 2 of 3
MEHRAZ NEGAR / PROJECT CONTROLS 02 MOHAMMADSAEED AZARSHAB | CONSTRUCTION PROJECT MANAGER 3 / 3 Management approach illustrated; required reviews and authorisations remain with responsible parties. A recovery proposal needs a delivery basis. MANAGEMENT APPROACH / HUMAN REVIEW & ACCOUNTABILITY 1 LOCATE Which constraint controls the milestone? 2 TEST Are access, resources and information ready? 3 REVIEW What are the cost, quality and safety implications? 4 AUTHORISE & TRACK Record the decision and check the new forecast. Preserve the baseline. Explain the recovery logic.
Visual 3 of 3

← All articles · View the original LinkedIn post →