Senior construction project management for selected fit-out and public-realm packages at Niayesh Mall. Coordinated contractors, consultants, suppliers and client representatives across commercial interiors, services interfaces and external works, including the 75-unit Level −1 Food Hall.
Coordinated tenant boundaries, shopfront fabrication, architectural finishes and building-services interfaces for the Food Hall, following authorised technical decisions through installation and close-out.
Coordinated architectural finishes, building-services interfaces and adjoining trade packages in cinema-level public areas; this does not claim specialist cinema-system design.
Coordinated the café refurbishment from existing-condition review and strip-out through shopfront preparation, fit-out installation and the completed green-awning frontage.
Coordinated external works and public-realm delivery, connecting groundworks, hardscape, landscape installation, lighting, drainage, services routes and street furniture.
Construction management case study
My role, decisions & delivery record
Programme recovery · contractor interfaces · procurement lead times · approved recovery cost · package handover
2 weeks
Recovered against delayed package forecast
Week 40
Actual handover of selected package
USD 18,000
Approved recovery budget
My role & scope
Senior Construction Project Manager for selected commercial fit-out and public-realm packages at Niayesh Mall, Tehran, September 2022–January 2026. I coordinated client representatives, consultants, contractors and suppliers across interiors, services interfaces and external works.
The challenge
Connected trade packages had to progress together while fabrication lead times affected the programme. In one selected package, a fabrication delay moved forecast completion from Week 40 to Week 42.
My actions & decisions
I reviewed programme logic, contractor capacity, lead times and recovery cost, then coordinated approved resequencing and split fabrication releases. A USD 18,000 recovery budget was approved for that package.
Result & delivery record
The selected package achieved actual handover in Week 40: two weeks recovered against the delayed Week 42 forecast. The wider portfolio separately records the Food Hall, leisure, restaurant, cinema public areas, café and external works.
Outcome scope: schedule recovery for one selected package. The 75-unit, approximately 5,500 m² Food Hall is presented as a separate portfolio entry.
Selected-package programme recovery, with technical delivery evidence presented in the separate Food Hall workstream.
Source drawings and record excerpts are identified separately from portfolio summaries and presentation visuals. Presentation visuals explain the project setting, including reference-based or presentation views; they are not original site or approval records.
Week 40Approved baseline
Week 42Delay forecast
USD 18,000Recovery approved
Week 40Actual handover
Protecting the selected-package milestonePortfolio outcome summary · selected package
A fabrication delay shifted the forecast by two weeks. Approved resequencing of two zones and split fabrication releases supported handover at the original Week 40 milestone.
My role: I reviewed programme logic, contractor capacity, procurement lead times and recovery cost, then coordinated the approved recovery action with supplier releases and site priorities.
Portfolio p. 04 · Schedule Recovery & Decision-Making; summary visualisation rather than an MS Project export
The captions identify the material shown. Illustrative studies, preliminary drawings and demonstration interfaces remain labelled as such in the portfolio record.
Further reading on the coordination topics relevant to this portfolio record. These guides do not imply that every method or software tool was used on this project.
Read about linking model information with sequencing and progress review.
Construction and architecture visual record
Images accompanying Niayesh Mall — Commercial Delivery: Commercial & Office Projects. The project description identifies Saeed Azarshab’s construction project management involvement; photographs, technical drawings and illustrations are identified individually in the captions.
تصاویر پروژهٔ Niayesh Mall — Commercial Delivery در مجموعهٔ فعالیتهای سعید آذرشب؛ سوابق تصویری ساختوساز، اجرا و معماری. نقش مدیریت پروژه و نوع هر تصویر، نقشه یا تصویر توضیحی در متن و زیرنویس همان پروژه مشخص شده است.
Professional opportunities
Discuss a construction management role
Explore my construction-delivery case studies and professional background, download my portfolio or get in touch.